From our experience space is often overlooked when designing IT
Network Infrastructures for Commercial Buildings. Below we have summarised the EIA/TIA-569-A
Pathways and Spaces Standard which most North American readers will probably be familiar with but few UK
readers.
Equipment Rooms
General design
considerations
A single centralised space
housing telecommunications equipment that serves a building.
-
common equipment may include a PBX, computing equipment
such as a mainframe and video switches
-
only equipment directly related to the telecommunications
system and its environmental support system is to be housed in the equipment room
-
ideally, the equipment room should be located close to the
main backbone pathway to allow for easier connected to the backbone pathway
Sizing issues
An equipment room is sized to
meet the known requirements of specific types of equipment.
Equipment room design should
allow for non-uniform building occupancy.
-
the recommended practice is to provide 0. 07 m2
of equipment room space for every 10 m2 of usable floor space (work areas.
-
if work area density is expected to be greater, provide
more equipment room space Multi-tenant building may have a single equipment room housing
equipment of all tenants, or each tenant may have individual equipment rooms dedicated to
their own equipment.
-
there
is also a factor which should be included for the equipment room size
calculation to encompass modern LAN based Building Management Systems (see
BMS Chapter in BiCSi Telecommunications Design Manual for details)
Special use buildings
(hospitals, hotels, etc.) should have equipment room space calculated on the basis of the
known number of work areas - not the usable floor area. Special consideration should be
given to Dealer Rooms.
Number of work areas
|
Equipment Room Size m2 |
Up to 100 |
14 |
101 to 400 |
37 |
401 to 800 |
74 |
801 to 1200 |
111 |
Other equipment room design issues
Ensure the floor loading
capacity is sufficient to bear both the distributed and concentrated load of installed
equipment.
The equipment room should not
be located below water level; preventative measures should be taken to prevent water
infiltration.
Consider also the following:
-
sources of electromagnetic interference, vibration, room
height, contaminants, sprinkler systems, HVAC equipment dedicated to the equipment room,
interior finishes, lighting, power, grounding, fire prevention
Note: More Detailed information can be obtained from
EIA/TIA-569 standard.
Telecommunications
Rooms/Closets
General design considerations
The location of the
Telecommunications Room should be as close as practical to the centre of the floor area
to be served.
It is preferred to locate
the TR in the core area
Closet space should not
be shared with electrical installations.
Size and spacing issues
It is recommended to have
at least one TR per floor; additional TRs are recommended when:
-
the usable floor area to be served is greater than 1000 m2
-
there should be one TR per 1000 m2 of usable
floor space
-
a rule-of-thumb estimates usable floor space at 75% of
total floor space
-
the length of the horizontal distribution cable required
to reach the work area is greater than 90 m (295 ft)
When there are multiple
TRs on
a single floor, it is recommended to interconnect these multiple closets with at least one
conduit (trade size 3) or equivalent.
Assuming one work area per 10 m2
the TR should be sized as follows:
Usable floor area m2 |
Closet Size m x m |
1,000 |
3 x 3.4 |
800 |
3 x 2.8 |
500 |
3 x 2.2 |
Other TR design issues
Floor loading is to be at least 2.4kPa (50 lbf/ft2).
Two walls are to be covered
with 2.6 m (8 ft) high, 20 mm (314 in) fire rated plywood to attach equipment.
Sufficient lighting is to be
provided; wall, floor and ceiling finishes should be light in colour to enhance room
lighting.
No false ceilings.
For powering equipment, at
least two dedicated duplex electrical outlets on separate circuits are to be provided; for
convenience, duplex electrical outlets should be placed at 1.8 m (6 ft) intervals around
perimeter walls.
There are instances when it is desirable to have a power
panel installed dedicated to serving the TR
Closet penetrations-sleeves,
slots, horizontal pathways-must be properly fire-stopped as per applicable codes.
Security and fire protection
are to be provided.
It is recommended to have
continuous HVAC-24 hours per day all year round.
Notes on TRs:
1.
More detailed information can be
obtained from EIA/TIA-569
2.
In the UK/Europe where historically
fully enclosed equipment cabinets have been used to mount equipment and connecting
hardware, there is not normally a requirement for plywood faced walls. Whereas
historically in North America connecting blocks have been wall mounted in TRs using
110, 66 or BIX blocks which requires the plywood faced walls. Also in North America equipment is often mounted
in open 19 frames and this necessitates that these be housed in a closet/room.
3.
In some instances in UK/Europe one will
find that in smaller installations the TR is not actually a self-contained room/closet. This approach is often due to space/cost issues
which can be overcome because in UK/Europe fully enclosed, securely locked equipment
cabinets are extensively used. An example of this room/closet-less Floor
Distributor (term used in ISO11801) may consist say of one/two floor standing 42U
high x 800 mm wide x 800 mm deep equipment cabinet/s located centrally within an open plan
office. Great care must be taken if this closet-less
un-recommended approach is used primarily with respect to life-safety, and expertise
should be sought. E.g. Fire Officer, BICSI RCDD, Office Space Planner.
Underground interbuilding backbone
pathway
An underground pathway is
considered to be a component of the entrance facility.
Pathway planning must consider the following: . limitations as dictated by
the topology; this includes land development . grading of the underground pathway to
permit proper drainage and the need to vent gaseous vapours
the amount of vehicle traffic
to determine the amount of cover over the pathway and whether or not concrete encasement
is required
Underground pathways consist of
conduits, ducts and troughs; possibly including manholes.
All conduits and ducts are to
have a diameter of 100 mm (4 in)
Bends are not recommended; if
required there should be no more than two 90 degree bends
Direct buried interbuilding backbone
pathway
A direct buried pathway is considered to be a component of
the entrance facility.
In such cases, the
telecommunications cables are completely covered in earth
Direct burial of
telecommunications cables is achieved by trenching, auguring or boring [pipe-pushing].
When selecting a route for the
pathway, it is important to consider the landscaping, fencing, trees, paved areas and
other possible services.
Aerial
interbuilding backbone pathway
An aerial pathway is considered
to be a component of the entrance facility.
In such cases, the facility
consists of poles, cable-support strand and support system.
Some considerations to make
when using aerial backbone include the following:
-
appearance - including the building and surrounding areas
-
applicable
codes
-
separation
and clearances for electrical and roads
-
span length, building attachments, storm loading and mechanical protection
-
number of cables currently and future growth potential
Tunnel
interbuilding backbone pathway
Tunnel pathways can be made of
conduit, trays, wire-ways or support strand.
The location of pathways within
a tunnel must be planned to allow for accessibility as well as for separation from other
services.
Intrabuilding backbone pathways
Vertical
backbone pathway
Made up of vertically aligned
telecommunications closets.
Lift shafts are NOT to be used
to locate backbone pathways.
Horizontal
backbone pathway
If a telecommunications closet
can not be vertically aligned with the one above or below.
Or if a closet cannot be vertically aligned with the entrance facility, then
a horizontal backbone pathway is used to connect them.
Design
issues
When using conduit (100 mm dia)
or sleeves, the following amount of backbone pathway is recommended:
-
one sleeve or conduit per 5000 m2 of usable floor space to be served by that backbone system
-
in addition, two spare sleeves or conduits for a total of
at least three.
Under floor duct
A system of rectangular
distribution and feeder ducts; a network of raceways embedded in concrete.
Distribution ducts - are those
ducts from which the wires and cables emerge to a specific work area.
Feeder ducts - are those ducts
which connect the distribution ducts to the telecommunications . closet.
For general office use, the
practice is to provide 650 mm2 of cross-sectional under floor duct area per 10
m2 of usable floor space-this applies to both distribution and feeder
ducts.
This is based on the following
assumptions:
Access
floor
Made up of modular floor panels
supported by pedestals with or without lateral bracing. - used in computer and equipment
rooms as well as general office areas it is necessary to design floor penetrations for the
type and number of work areas.
Conduit
Conduit types include
electrical metallic tubing, rigid metal conduit and rigid PVC.
-
the type of conduit used must be permitted under the
appropriate electrical codes metal flex conduit is not recommended due to possible
cable abrasion problems Using conduit for a horizontal raceway system for
telecommunications cabling should be considered only when:
-
telecommunications outlet locations are permanent
-
device densities are low
-
flexibility is not a requirement
Installed conduit has
requirements for support, end protection and continuity as specified in appropriate
electrical codes.
Cable trays
and wire-ways
These are rigid structures for
the containment of telecommunications cables.
Trays and wire-ways can be
located above or below the ceiling in plenum or non-plenum applications.
For general office use, the
practice is to provide 650 mm2
of cross-sectional tray or wire-way area per 10 m2
usable floor space or work area.
This is based on the following
assumptions:
Ceiling pathway
Conditions for ceiling
distribution systems include the following:
-
inaccessible ceiling areas [lock-in ceiling tiles,
drywall, plaster] are not to be used as distribution pathways
-
ceiling tiles must be removable and placed at a maximum
height of 3.4 m (11 ft) above the floor
-
there must be adequate and suitable space available in the
ceiling area for the recommended distribution layout-a minimum of 75 mm (3 in) of clear
vertical space must be available
-
there must be a suitable means and methods for supporting
cables and wires-they are not to be laid directly on the ceiling tile or rails.
-
raceways are to be provided where required by codes or
design
Perimeter
raceways
Used to serve work areas where
telecommunications devices can be reached from walls at convenient levels.
The determining factor for
using perimeter pathways is room size.
Not covered
by standard
Over-floor raceways
Exposed wiring
Poke-thru
Curtain wall
Work Area
Work areas
Recommendations for work areas
cover only specifications for telecommunications pathways and telecommunications outlets.
Work area telecommunications
pathways
Furniture pathways
-
if telecommunications pathways are to be incorporated into
furniture or partitions, they must comply with:
-
all applicable electrical codes
-
UL 1286, "Office Furnishings"
-
manufacturers should be consulted to determine raceway
capabilities and optional features available.
Reception areas, control
centres, attendant areas
-
these areas typically have heavy demands for
telecommunications equipment
-
it is recommended to have independent, direct pathways to
these areas from the telecommunications closet
Telecommunications
outlets
A typical example of such a
connection point is a 100 x 100 mm (4 x 4 in...in USA much smaller in the UK) electrical
box with horizontal cable terminated on faceplate connectors.
-
telecommunications devices in the work area are connected
to the faceplate It is necessary to consider the number and type of devices to be
connected.
-
typical telecommunications devices include telephones,
personal computers, graphic or video terminals, fax machines, modems
At least one outlet box should
be provided to each work area.
*for areas where it will be
difficult to add telecommunications outlet boxes at a later time, at least two separate
outlets are recommended for initial installation; to maximise flexibility they should be
located to allow for a change in office design [e.g. locate outlet boxes on opposite
walls]
Most
of the major American standards relating to structured cabling are published
under the auspices of ANSI/TIA/EIA.